Progress
Where the works stand
The two houses move through declared phases. Here is the pace of each, without convenient rounding: every sub-step carries its share, so that even a small advance stays visible.
The percentages measure technical progress on the planned works, not expenditure. Updated September 2026.
Riad Al-Uns
رياض الأُنس
Fez, Morocco — house of hospitality and training
One segment per phase: pre-design, Phase 0, Phase 1, Phase 2, opening.
01Pre-designUnder way44%
The papers, the concept, the working team.
-
Legal and notarial due diligenceUnder way30%
Draft legal texts: early progress on due diligence.
-
Concept and functional briefCompleted100%
Last update: 2026·07
-
Team appointment and preliminary commissionsUnder way20%
Last update: 2026·08
-
Preliminary budgetCompleted100%
Last update: 2026·09
-
Archive and land-registry researchUnder way50%
Last update: 2026·09
-
First meetings with the architects appointed to survey the candidate propertiesUnder way10%
Last update: 2026·09
-
Presenting the project to the patrons and gathering applications from the founding members of the NudamaNot started0%
02Phase 0 — Surveys, diagnostics and permitsNot started0%
Knowing the building and earning leave to touch it.
-
Material diagnostics and samplingNot started0%
-
Heritage procedures and building permitsNot started0%
-
Detailed design approvedNot started0%
03Phase 1 — Structure and servicesNot started0%
The body of the building and its service runs.
-
Consolidation and making safeNot started0%
-
Roofs and floor structures rebuiltNot started0%
-
Hydraulic and electrical runs integratedNot started0%
04Phase 2 — Finishes, art crafts and furnishingNot started0%
The craftsman's hand, where the eye rests.
-
Zellige and hand-made tileworkNot started0%
-
Tadelakt and lime plastersNot started0%
-
Traditional joineryNot started0%
-
Lighting design and fit-outNot started0%
05OpeningNot started0%
Sign-off, outfitting, first hospitality.
-
Technical sign-off and occupancyNot started0%
-
Hospitality fit-outNot started0%
-
Soft openingNot started0%
-
InaugurationNot started0%
Al-Funduq as-Siqilli
الفندق الصقلّي
Sicily — house of crafts and welcome
One segment per phase: pre-design, Phase 0, Phase 1, Phase 2, opening.
01Pre-designUnder way51%
The papers, the concept, the working team.
-
Legal and notarial due diligenceNot started0%
-
Concept and functional briefCompleted100%
Last update: 2026·07
-
Team appointment and preliminary commissionsUnder way5%
Last update: 2026·08
-
Preliminary budgetCompleted100%
Last update: 2026·09
-
Archive and land-registry researchUnder way50%
Last update: 2026·09
-
First meetings with the architects appointed to survey the candidate propertiesUnder way5%
Last update: 2026·09
-
Presenting the project to the patrons and gathering applications from the founding members of the NudamaNot started0%
-
Constitution of the “Il Fondaco Siciliano” associationCompleted100%
Association constituted; awaiting the tax code from the Agenzia delle Entrate.
Last update: 2026·09
-
Option on the propertyCompleted100%
Option signed on the property: valid until 25 March 2027.
02Phase 0 — Surveys, diagnostics and permitsNot started0%
Knowing the building and earning leave to touch it.
-
Material diagnostics and samplingNot started0%
-
Heritage procedures and building permitsNot started0%
-
Detailed design approvedNot started0%
03Phase 1 — Structure and servicesNot started0%
The body of the building and its service runs.
-
Consolidation and making safeNot started0%
-
Roofs and floor structures rebuiltNot started0%
-
Hydraulic and electrical runs integratedNot started0%
04Phase 2 — Finishes, art crafts and furnishingNot started0%
The craftsman's hand, where the eye rests.
-
Saddlery and leatherworkNot started0%
-
Joinery and traditional timberNot started0%
-
Wrought iron and metalworkNot started0%
-
Lighting design and fit-outNot started0%
05OpeningNot started0%
Sign-off, outfitting, first hospitality.
-
Technical sign-off and occupancyNot started0%
-
Hospitality fit-outNot started0%
-
Soft openingNot started0%
-
InaugurationNot started0%
Opening dates are announced once the preceding phase is closed and signed off. For the sites, craft commissions or support, there is a single way: the contact page.